Which term refers to a list of unfinished items that must be completed by the contractor before contract completion?

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question is equipped with hints and detailed explanations. Get ready for a career leap!

Multiple Choice

Which term refers to a list of unfinished items that must be completed by the contractor before contract completion?

Explanation:
A punch list is the compilation of unfinished items identified during a final walk-through that the contractor must complete to finish the project. It typically appears as the work approaches substantial completion and includes tasks like cosmetic touch-ups, missing hardware, or deficiencies that prevent final acceptance. Addressing all items on the punch list allows the project to move to final completion and closeout. The other terms describe different stages or tools: substantial completion marks the project being ready for use, beneficial occupancy allows use before final closeout, and a general check list is a broad administrative tool rather than the specific list of remaining work.

A punch list is the compilation of unfinished items identified during a final walk-through that the contractor must complete to finish the project. It typically appears as the work approaches substantial completion and includes tasks like cosmetic touch-ups, missing hardware, or deficiencies that prevent final acceptance. Addressing all items on the punch list allows the project to move to final completion and closeout. The other terms describe different stages or tools: substantial completion marks the project being ready for use, beneficial occupancy allows use before final closeout, and a general check list is a broad administrative tool rather than the specific list of remaining work.