Which technique uses additional resources to shorten the project schedule by compressing critical activities?

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question is equipped with hints and detailed explanations. Get ready for a career leap!

Multiple Choice

Which technique uses additional resources to shorten the project schedule by compressing critical activities?

Explanation:
Crashing is the technique that uses additional resources to shorten the project schedule by compressing critical activities. Since the overall finish date is dictated by the critical path, the only way to shorten the project duration is to shorten tasks on that path. By adding people, equipment, or overtime to those critical tasks, you can reduce their durations and thus finish sooner. This comes with higher costs and increased coordination risk, but it specifically targets the activities that determine the schedule. Fast tracking would shorten the schedule by overlapping tasks without extra resources, the Critical Chain Method uses buffers and focuses on resource constraints to protect the timeline, and the Critical Path Method identifies which tasks form the critical path but does not itself shorten the project.

Crashing is the technique that uses additional resources to shorten the project schedule by compressing critical activities. Since the overall finish date is dictated by the critical path, the only way to shorten the project duration is to shorten tasks on that path. By adding people, equipment, or overtime to those critical tasks, you can reduce their durations and thus finish sooner. This comes with higher costs and increased coordination risk, but it specifically targets the activities that determine the schedule. Fast tracking would shorten the schedule by overlapping tasks without extra resources, the Critical Chain Method uses buffers and focuses on resource constraints to protect the timeline, and the Critical Path Method identifies which tasks form the critical path but does not itself shorten the project.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy