Which document is issued by a principal directing changes in a contract authorized under the contract's changes clause?

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question is equipped with hints and detailed explanations. Get ready for a career leap!

Multiple Choice

Which document is issued by a principal directing changes in a contract authorized under the contract's changes clause?

Explanation:
When the owner needs to direct a modification to the work under the contract’s changes clause, the instrument used is a Site Instruction. This document comes from the principal (or their on-site representative) and provides explicit directions to alter, clarify, or add to the work so the project can proceed. It serves as a quick, on-site directive to implement needed changes, with any resulting impact on cost or schedule addressed later through the contract’s formal change processes. A Non-conformance Report records defects and required corrective action, not a directive to change the contract. A Contract Change Notification is a formal notice that a change is being proposed or has occurred, and a Change Control Board is the group that reviews and approves changes, not a specific on-site directive.

When the owner needs to direct a modification to the work under the contract’s changes clause, the instrument used is a Site Instruction. This document comes from the principal (or their on-site representative) and provides explicit directions to alter, clarify, or add to the work so the project can proceed. It serves as a quick, on-site directive to implement needed changes, with any resulting impact on cost or schedule addressed later through the contract’s formal change processes. A Non-conformance Report records defects and required corrective action, not a directive to change the contract. A Contract Change Notification is a formal notice that a change is being proposed or has occurred, and a Change Control Board is the group that reviews and approves changes, not a specific on-site directive.