Which clause should be stated in Time & Material contracts?

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question is equipped with hints and detailed explanations. Get ready for a career leap!

Multiple Choice

Which clause should be stated in Time & Material contracts?

Explanation:
In time and materials work, costs can drift because you’re paying for actual hours and materials rather than a fixed price. A clause that governs exceeding the agreed budget is essential. The Exceed clause sets a cost ceiling or requires written approval before any amount beyond a defined limit is spent, giving both owner and contractor a clear process to manage overruns. This protects the owner from surprise bills and gives the project a controlled path to continue if scope grows, with explicit authorization. Indemnity provisions address risk transfer but don’t directly control how costs are managed in a T&M setup. Early completion and penalty clauses are not typical tools for managing the variable pricing of T&M contracts and can introduce undesired incentives or disputes.

In time and materials work, costs can drift because you’re paying for actual hours and materials rather than a fixed price. A clause that governs exceeding the agreed budget is essential. The Exceed clause sets a cost ceiling or requires written approval before any amount beyond a defined limit is spent, giving both owner and contractor a clear process to manage overruns. This protects the owner from surprise bills and gives the project a controlled path to continue if scope grows, with explicit authorization.

Indemnity provisions address risk transfer but don’t directly control how costs are managed in a T&M setup. Early completion and penalty clauses are not typical tools for managing the variable pricing of T&M contracts and can introduce undesired incentives or disputes.