When estimating expenses to ensure they stay within budget, which stage is NOT typically estimated?

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question is equipped with hints and detailed explanations. Get ready for a career leap!

Multiple Choice

When estimating expenses to ensure they stay within budget, which stage is NOT typically estimated?

Explanation:
Estimating expenses is done repeatedly as the design evolves to keep the budget aligned with what’s being built. Early on, rough estimates at the preliminary design stage help assess feasibility, then at schematic design you refine the cost, and during the in-progress final design (roughly 60%–90% complete) you update the estimate with more detail and current unit costs to tighten the budget. By the end of the Project Life Cycle, there isn’t a forward-looking estimate needed to control costs—the project is finished, and the focus shifts to capturing actual costs and final closeout. Post-project analyses may look at life-cycle or operations costs, but these don’t drive the construction budget during execution.

Estimating expenses is done repeatedly as the design evolves to keep the budget aligned with what’s being built. Early on, rough estimates at the preliminary design stage help assess feasibility, then at schematic design you refine the cost, and during the in-progress final design (roughly 60%–90% complete) you update the estimate with more detail and current unit costs to tighten the budget. By the end of the Project Life Cycle, there isn’t a forward-looking estimate needed to control costs—the project is finished, and the focus shifts to capturing actual costs and final closeout. Post-project analyses may look at life-cycle or operations costs, but these don’t drive the construction budget during execution.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy