Multiple Choice

What term refers to items that are unfinished or do not meet specified requirements and must be completed by the contractor before contract closeout?

Explanation:
Items that are unfinished or don’t meet requirements to be completed before contract closeout are called a punch list. This list is usually created during the final walkthrough with the owner, architect, and contractor, and it itemizes deficiencies or incomplete work that the contractor must correct. Each entry specifies what needs to be done, who is responsible, and a target date for completion. Only after all punch list items are resolved and the work complies with the contract documents can closeout proceed and final payments be issued. This concept is distinct from non-conformances, which are quality issues found during the project at any time, not just at the end. A general checklist is a broader tool used for verifying tasks, and an unbilled amount refers to unpaid invoices rather than construction defects or closeout work.

Items that are unfinished or don’t meet requirements to be completed before contract closeout are called a punch list. This list is usually created during the final walkthrough with the owner, architect, and contractor, and it itemizes deficiencies or incomplete work that the contractor must correct. Each entry specifies what needs to be done, who is responsible, and a target date for completion. Only after all punch list items are resolved and the work complies with the contract documents can closeout proceed and final payments be issued. This concept is distinct from non-conformances, which are quality issues found during the project at any time, not just at the end. A general checklist is a broader tool used for verifying tasks, and an unbilled amount refers to unpaid invoices rather than construction defects or closeout work.