The following are considered to recover the schedule, EXCEPT:

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question is equipped with hints and detailed explanations. Get ready for a career leap!

Multiple Choice

The following are considered to recover the schedule, EXCEPT:

Explanation:
Handling schedule recovery involves the CM asking the contractor to lay out a concrete recovery schedule showing how lost time will be made up, evaluating that plan, and insisting on revisions if needed. The emphasis is on plans that actually restore progress through real actions—like adding crews or working overtime—rather than manipulating the schedule by shrinking durations or overlapping work inappropriately. The option that does not fit is the idea that, if a recovery plan is rejected, the rejected plan should be incorporated into the construction schedule. Once a plan is deemed unacceptable, it should not be inserted into the schedule; instead, the contractor is expected to submit a new, acceptable plan. That iterative revision process is central to effective schedule recovery. The other approaches align with proper practice: initiating a recovery plan, evaluating and potentially rejecting it while requiring a better one, and focusing on tangible acceleration efforts rather than artificial duration cuts.

Handling schedule recovery involves the CM asking the contractor to lay out a concrete recovery schedule showing how lost time will be made up, evaluating that plan, and insisting on revisions if needed. The emphasis is on plans that actually restore progress through real actions—like adding crews or working overtime—rather than manipulating the schedule by shrinking durations or overlapping work inappropriately.

The option that does not fit is the idea that, if a recovery plan is rejected, the rejected plan should be incorporated into the construction schedule. Once a plan is deemed unacceptable, it should not be inserted into the schedule; instead, the contractor is expected to submit a new, acceptable plan. That iterative revision process is central to effective schedule recovery. The other approaches align with proper practice: initiating a recovery plan, evaluating and potentially rejecting it while requiring a better one, and focusing on tangible acceleration efforts rather than artificial duration cuts.