In scheduling, what does LS stand for?

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question is equipped with hints and detailed explanations. Get ready for a career leap!

Multiple Choice

In scheduling, what does LS stand for?

Explanation:
Late Start. In CPM scheduling, each activity has an earliest start (ES) and a latest start (LS) along with the corresponding finish times. Late Start is the latest time an activity can begin without delaying the project's finish date, given the required durations and dependencies. It is found from LS = LF − duration, where LF is the latest finish. This helps determine float: slack = LS − ES. If slack is zero, the activity is on the critical path and delaying it would delay the project. The other terms listed aren’t standard CPM terminology.

Late Start. In CPM scheduling, each activity has an earliest start (ES) and a latest start (LS) along with the corresponding finish times. Late Start is the latest time an activity can begin without delaying the project's finish date, given the required durations and dependencies. It is found from LS = LF − duration, where LF is the latest finish. This helps determine float: slack = LS − ES. If slack is zero, the activity is on the critical path and delaying it would delay the project. The other terms listed aren’t standard CPM terminology.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy