During pre-design on a design-bid-build project, the owner is concerned about reducing risk. Which delivery method should you recommend?

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question is equipped with hints and detailed explanations. Get ready for a career leap!

Multiple Choice

During pre-design on a design-bid-build project, the owner is concerned about reducing risk. Which delivery method should you recommend?

Explanation:
Bringing in a construction manager early to work with the design team reduces risk by providing constructability input, detailed cost guidance, and a fixed price ceiling as the project progresses. In a construction management at-risk arrangement, the CM is engaged during design and later commits to a guaranteed maximum price for the work. This means cost estimates are tied to real constructability considerations, procurement sequencing is planned upfront, and the CM assumes the cost risk for overruns beyond the GMP (subject to agreed exceptions). With this setup, design decisions can be steered to stay within budget and schedule, and potential changes or value-engineering opportunities can be identified early, before they become costly surprises. The other approaches don’t offer the same level of early cost control and risk transfer. Multiple-prime contracting increases owner risk and coordination challenges because many prime contractors must be managed and integrated. Design-bid-build keeps the designer and contractor separate, so there’s little contractor input during design, which can lead to cost growth and scheduling issues later. Integrated project delivery aims for maximum collaboration and shared risk, but it requires a different contractual framework and team alignment that isn’t always feasible in a pre-design phase of a traditional design-bid-build project.

Bringing in a construction manager early to work with the design team reduces risk by providing constructability input, detailed cost guidance, and a fixed price ceiling as the project progresses. In a construction management at-risk arrangement, the CM is engaged during design and later commits to a guaranteed maximum price for the work. This means cost estimates are tied to real constructability considerations, procurement sequencing is planned upfront, and the CM assumes the cost risk for overruns beyond the GMP (subject to agreed exceptions). With this setup, design decisions can be steered to stay within budget and schedule, and potential changes or value-engineering opportunities can be identified early, before they become costly surprises.

The other approaches don’t offer the same level of early cost control and risk transfer. Multiple-prime contracting increases owner risk and coordination challenges because many prime contractors must be managed and integrated. Design-bid-build keeps the designer and contractor separate, so there’s little contractor input during design, which can lead to cost growth and scheduling issues later. Integrated project delivery aims for maximum collaboration and shared risk, but it requires a different contractual framework and team alignment that isn’t always feasible in a pre-design phase of a traditional design-bid-build project.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy