Back charging is NOT a result of:

Prepare for the CMAA Construction Management Exam. Study with flashcards and multiple choice questions, each question is equipped with hints and detailed explanations. Get ready for a career leap!

Multiple Choice

Back charging is NOT a result of:

Explanation:
Back charging happens when the owner recovers costs incurred because the contractor didn’t meet contract requirements or caused extra expenses—such as rework due to non-conformances, failure to deliver what was agreed, or delays that push up costs. These situations create additional charges or deductions as a remedy for the incurred costs. In contrast, progress the contractor makes is a normal part of the job that is expected and typically reflected in regular payments; it does not generate back charges. So the statement that back charging is not a result of progress made by the contractor is the correct choice.

Back charging happens when the owner recovers costs incurred because the contractor didn’t meet contract requirements or caused extra expenses—such as rework due to non-conformances, failure to deliver what was agreed, or delays that push up costs. These situations create additional charges or deductions as a remedy for the incurred costs. In contrast, progress the contractor makes is a normal part of the job that is expected and typically reflected in regular payments; it does not generate back charges. So the statement that back charging is not a result of progress made by the contractor is the correct choice.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy